BIG STORY

Port-Harcourt Refinery Still Under Test-Running — NNPCL

Published

on

Port Harcourt Refinery is still test-running in order to guarantee operational readiness before the commencement of commercial operations.

Following a Turn Around Maintenance, or TAM, the refinery was scheduled to start up again in December 2023. However, according to checks done yesterday by Energy Vanguard, the exercise is still in progress and would be followed by the supply of crude oil.

Chief Corporate Communications Officer, NNPC Ltd., Olufemi Oladapo Soneye, who confirmed the development, said: “We have said that the Port Harcourt Refinery has been completed. Test running is ongoing. It is targeted at ensuring that everything, including the lines, is in perfect condition. It is when everything is confirmed to be fine that supply of crude for refining can start.”

Previously, NNPC Ltd. had said it achieved the mechanical completion of rehabilitation work on the Area 5 Plant of the Port Harcourt Refining Company (PHRC).

According to NNPC Ltd., “Rehabilitation work has been ongoing at the Refinery for over two years and the NNPC Ltd. had pledged to complete Phase One of the project (mechanical completion and flare start-up) of Old Port Harcourt Refinery (Area 5) by 31st December 2023.”

Speaking during an inspection tour of the rehabilitation project, which also coincided with the 15th Refineries’ Rehabilitation Steering Committee Meeting, the Group Chief Executive Officer, NNPC Ltd., Mr. Mele Kyari, had said as of December 15th, 2023, 84.4% of Area 5 Plant, a key component of the Refinery, and 77.4% of the entire rehabilitation project have been completed.

He said: “In our quest to ensure that this refinery is re-streamed to continue to deliver value to Nigerians, we made a promise that we will reach a mechanical completion of phase one of the rehabilitation project by the end of December and get the other plants running in 2024. Today, we have kept those commitments.”

Similarly, the Chairman of the NNPC Ltd Board, Pius Akinyelure described the milestone as “historic”, stressing that the board was proud of the staff and management of the refinery.

“We are just starting. We want to be at the highest level of production so that we will keep the prices of petroleum prices in the country stable to give comfort to our people and generate more revenue for our country,” Akinyelure noted.