Connect with us


BIG STORY

FG May Place The “Free Four Million Meters” Distribution On Hold

Published

on

The Federal Government-funded Phase 1 of the National Mass Metering Programme, NMMP, slated to commence in August appears to have been mired in uncertainty, as it had been put on hold following allegations of fraud by the Central Bank of Nigeria against some of the Meter Asset Providers, MAPs.

A source, who pleaded anonymity due to the sensitivity of the matter, said that there was no indication that the Phase 1 meter distribution would commence this month, as power distribution companies were yet to be furnished with meters.

The NMMP is an initiative of the Nigerian Electricity Regulatory Commission, NERC, in conjunction with the Presidential Power Task Force. The initiative was launched in August 2020 to allow the CBN to fund the acquisition of meters on behalf of DisCos by paying directly to the MAPs. The free metering programme commenced with the Phase 0 where one million meters were supposed to have been distributed.

However, the CBN, on July 20, asked the Federal High Court in Lokoja, Kogi State, to freeze accounts belonging to 157 MAPs for allegedly diverting funds meant for the procurement of prepaid meters.

The apex bank, in a suit, requested commercial banks to restrict the account of 10 companies that received power sector intervention funds under the NMMP for 180 days pending the outcome of its investigation.

Report has it that the free mass programme had also been put on hold until further notice, following the ongoing court case.

One of our sources said that the DisCos had accused some MAPs of not supplying them with enough meters during the last visits by the CBN to the DisCos’ offices.

“The CBN visited the DisCos to audit their books and see what they used the intervention funds given to them for. It was during the visits that it was discovered that some of the MAPs had failed to deliver enough meters for distribution. Before the NMMP commenced; what we were told by the MAPs was that they had enough local capacity to meet demands. But after the CBN signed the contract with them and disbursed money to them, they failed to meet their target. They saw free money,” one of our sources had hinted.

The CBN, in the suit said, “The Central Bank of Nigeria reviewed the activities of 12, including the defendants herein Meter Asset Providers (MAPs) alleged to have diverted the Central Bank of Nigeria’s power sector intervention funds under the National Mass Metering Programme (NMMP).

“The review was aimed at ascertaining the flow of the funds made available to the MAPs, covering the period between January 1, 2020, to March 15, 2022. The preliminary review revealed that the defendants diverted a substantial portion of the funds for other uses through related entities and individuals/companies connected to the electricity distribution companies (DisCos) and the defunct Power Holding Company of Nigeria (PHCN),” the suit partly said.

Nigeria’s central bank has invested heavily into the power sector through its intervention support programmes. According to the bank, it had disbursed over N254.4 billion through its Nigeria Electricity Market Stabilization Facility – Phase 2, NEMSF-2.

At the last Monetary Policy Committee meeting of the Central Bank, Governor Godwin Emefiele revealed it disbursed about N47.8 billion for about 865,956 meters across the country.

“Under the National Mass Metering Programme (NMMP), the Bank disbursed N47.82 billion for the procurement and installation of 865,956 meters across the country.”

Spokesperson for CBN, Osita Nwanisobi, declined commenting on the matter when contacted.

The NERC, on its part, said it created the initiative in response to President Buhari’s order that Nigerians must be metered. “The President has directed that there should be a nationwide mass-metering program in an effort by the Federal Government to put a stop to estimated and arbitrary billing for electricity.”

The Commission had recently spoken of the success of Phase 0, and revealed it had shortlisted 45 companies for the next phase. It added that; “We are hoping that before the end of August, we will begin to see meters from our local manufacturers going to the electricity Distribution Companies and then to end-user customers.”

Both calls and messages put through to the General Manager/Head of Public Affairs Department, NERC, Usman Abba Arabi, were not responded to as at the time of filing this report.

One of the accused MAPs, Mojec Meter Asset Management Company Ltd, said that it fully discharged its obligations of manufacturing, supplies, and installation of meters for all eight DisCos it was assigned to. The company also pointed out that it was issued certificates of completion by all the eight DisCo clients as proof of execution of its contractual obligations on the initiative, according to Corporate Communications Manager, MOJEC International Group, Olufunso Adeolu.

“Mojec is ready to release all meter serial numbers produced in its factories, together with records of waybills of all in-Country volumes of meters it delivered to the various DisCos under the initiative,” Adeolu added.

Other accused MAPs were yet to make any comments on the matter as at the time when this report was filled.

Metering Expert, Okunade Sesan, said that it was better for the NMMP to be scrapped so that citizens would be allowed to buy their own meters.

“The CBN refusing to disburse funds for the next phase of the metering is going to cause a setback. It would even be better for electricity consumers to take their fate into their hands and buy their meters. Then, NERC can arrange for monthly refunds through electricity units,” he said.

BIG STORY

Four Nigerian Students Jailed In UK For Fighting With Knives, Baseball Bats

Published

on

Four Nigerian students have been sentenced in the United Kingdom for their involvement in a violent altercation that involved knives and a baseball bat in Leicester.

The incident, which took place on New Park Street in the early hours of November 4, 2021, left one victim with multiple stab wounds.

Following a thorough investigation by the Leicester City Police, authorities identified the culprits through CCTV footage, phone tracking, and public assistance.

The six-week trial concluded in October, and the sentences were delivered on November 14.

A report published on the police website last Thursday provided details of the outcome.

Destiny Ojo (21), of Plumstead, London, was sentenced to seven years for violent disorder, attempted grievous bodily harm (GBH), and GBH with intent.

Habib Lawal (21), of Bexley, London, was sentenced to five years for violent disorder, attempted GBH, and GBH with intent.

Ridwanulahi Raheem (21), of Lambeth, London, was sentenced to three years for violent disorder and possession of a bladed article.

Joshua Davies-Ero (21), of Bexley, London, was sentenced to two years for violent disorder.

A fifth defendant, Justin Asamoah (22), of Merton, had earlier pleaded guilty to possession of a bladed article and is scheduled to be sentenced on November 22.

A spokesperson for Leicester Police praised the public for their help during the investigation and emphasized the importance of addressing violent behavior to ensure community safety.

Detective Constable Sean Downey, commenting on the case, said, “This incident underscores the grave dangers of violent disorder. It is fortunate that the injuries sustained were not more severe or fatal. This could have been a very different investigation.”

He added, “We thank everyone who supported the investigation. As a force, our priority is public safety. Violent behavior will not be tolerated in our communities, and we will continue to take decisive action against offenders.”

Continue Reading

BIG STORY

Enugu LGA Chairman Appoints Aides On Garden Egg, Pepper, Yam

Published

on

Eric Odo, chairman of Igbo Etiti LGA in Enugu state, has appointed Ezeugwu Ogbonna as senior special assistant on agriculture (yam and pepper).

The appointment was formalized in a letter dated November 1, addressed to Ogbonna.

“I am pleased to inform you that the executive chairman Igbo Etiti LGA has approved your appointment as senior special assistant to the local government chairman on agriculture (yam and pepper),” the letter states.

“You should report to the executive chairman Igbo Etiti LGA, Ogbede, for briefing and deployment,” it continues.

“It is pertinent to note that this is not a career civil service appointment but a temporary appointment which you hold at the pleasure of the executive chairman of Igbo Etiti LGA,” the letter further clarifies.

Odo also appointed Nwodo Ugonna as special adviser on garden egg and pepper.

The council chairman did not specify the exact duties of the appointees.

Continue Reading

BIG STORY

NNPCL Admits Challenges Delaying Port Harcourt Refinery Take-Off

Published

on

Barely two months after the September completion deadline flop, the Nigerian National Petroleum Commission (NNPC) has explained why it could not deliver the much-awaited Port Harcourt Refinery Company.

In an interview (with The Punch) on Monday, the NNPC Chief Corporate Communications Officer, Olufemi Soneye, said the company encountered risks and challenges while carrying out the rehabilitation, being a brownfield project.

He noted that the NNPC began the commissioning of critical equipment and processing units after the mechanical completion in Nigeria.

“You may recall that mechanical completion of the PHRC revamp was successfully achieved several months ago, marking a significant milestone in the project. Following this, we began the commissioning of critical equipment and process units.”

“However, as is common with brownfield projects of this scale and complexity, we encountered unforeseen risks and challenges,” he stated.

Nonetheless, he told (The Punch) that the issues were resolved and commissioning activities have resumed.

Soneye stressed that work is being carried out to ensure the project’s completion.

“These issues have since been effectively resolved, and commissioning activities have resumed.”

“Work is being carried out around the clock to ensure the successful completion of this critical project,” he told our correspondent.

Asked if there is any timeline for the completion of the project, he replied, “Shortly.”

It was observed that the NNPC desisted from giving new deadlines for the delivery of the refinery, having failed to meet its deadlines seven times.

The moribund Port Harcourt refinery is one of three owned by the Federal Government and managed by the NNPC.

Nigerians have been hopeful that the cost of fuel could crash if the country refines its crude and ends the import of refined products.

The NNPC said last week that it would continue to import fuel, saying it was not the sole off-taker of petrol at the Dangote refinery.

The refinery, situated in Nigeria’s oil-rich Niger Delta region, has been in operation since 1965, but later became moribund for several years.

In March 2021, the Nigerian government acquired a $1.5bn loan for the renovation and modernisation of the refinery, but the contractor handling the project has yet to announce its completion.

It was gathered that promises made to Nigerians by the Federal Ministry of Petroleum Resources and the NNPC about the refinery have continued to hit brick walls.

After the failure of the sixth deadline in early August, the then Chief Financial Officer of the NNPC, Umar Ajiya, said the refinery would commence operations in September 2024.

However, September ended without a word from the NNPC about the refinery, and Nigerians have been left in the dark since almost two months ago.

Recall that the contractor overseeing the rehabilitation of the Port Harcourt refinery, Maire Tecnimont SPA, refused to disclose the completion date for the project, despite a formal request from a human rights lawyer, Femi Falana.

Apparently baffled by the delay in the completion of the project, Falana had filed an official request under the Freedom of Information Act, seeking clarity on the date set aside for the project completion.

In response, Maire Tecnimont’s legal representative, Muyiwa Ogungbenro, a partner at Olajide Oyewole LLP, sent a letter to Falana in early October, declining to reveal the information.

Ogungbenro stated that the Managing Director of Maire Tecnimont SPA, as part of an independent private contractor, is not obligated to disclose such information under the FOI Act.

“We are counsel to Maire Tecnimont SpA, and we have our client’s instruction to respond to your letters dated 17 and 24 September 2024 requesting information on the contract between our client and Nigerian National Petroleum Company Ltd.

“Our client is a private company. Being a private independent contractor, our client is not a company in which any government has a controlling interest, and does not provide public services, functions or utilise public funds for them to be bound by the obligations in the Freedom of Information Act.

“On this ground, our client regrettably cannot provide the information you have requested,” Ogungbenro declared.

Since then, information about the refinery has been kept from the public, whose hope for cheaper petrol lies in the facility.

From December 2023, NNPC had been giving Nigerians different dates, assuring them that the refinery would begin the sale of refined products soon, having attained mechanical completion.

In July, the Group Chief Executive Officer of the NNPC, Mele Kyari, stated categorically that the refinery would come into operation in early August. He had said in 2019 that the NNPC would deliver all the country’s four refineries before the end of former President Muhammadu Buhari’s administration last year.

When he appeared before the Senate in July, Kyari boasted, “I can confirm to you, Mr Chairman, that by the end of the year, this country will be a net exporter of petroleum products.

“Specific to NNPC refineries, we have spoken to a number of your committees, and it is impossible to have the Kaduna refinery come into operation before December, it will get to December, both Warri and Kaduna; but that of Port Harcourt will commence production early August this year.”

However, the promise was not fulfilled in August which was the sixth postponement.

Though the NNPC said it was on course, the refinery has yet to commence operations even as the fourth quarter of the year nears the end.

Recall that the 210,000 barrels per day refinery was said to have reached what the NNPC called mechanical completion of rehabilitation work in December. It stated that the facility would start refining 60,000 barrels of crude oil daily after last year’s Christmas break.

Later in January, Kyari said the refinery was being tested and would be ready by the end of the first month.

During the second month of the year, the Shell Petroleum Development Company of Nigeria Limited completed the supply of 475,000 barrels of crude oil to the facility, raising the expectations of marketers that production would soon start.

This came a few weeks after the NNPC said in January that it was seeking to engage reputable and credible operations and maintenance companies to run the refinery.

In mid-March, Kyari said the Port Harcourt refinery would commence operations in two weeks, April.

“We are serving this country with honour and dignity. And we will make sure that the promises we make on the rehabilitation of these refineries will take place,” Kyari stated after he appeared before the Senate Ad-hoc Committee investigating the various turnaround maintenance projects of the country’s refineries.

As the April deadline elapsed, independent petroleum marketers told (The Punch) that the facility would begin production by the end of July.

Commenting on this then, NNPC’s spokesman, Soneye, said that regulatory approvals from international bodies were the only impediment stalling the operational commencement of the refinery.

 

Credit: The Punch

Continue Reading



 

Join Us On Facebook

Most Popular